[tech] Machine Room Switch Upgrade - TL;DR
James Arcus
jimbo at ucc.asn.au
Sat Jul 13 12:35:54 AWST 2019
I know my previous email was quite long, so I thought I'd just summarize
the main points here.
* New switch was installed, is faster and newer and lets us use 10
Gb/s fibre
* We now have a 10 Gb/s link from the machine room servers to the rest
of our network
* Everything else should be working the same, if it isn't contact me
or [FVP]
* Cisco switches are heavy and difficult to lift
* Lifting them directly up into place, instead of moving them up and
sideways to the rack from outside it, is much easier
Cheers,
James [MPT]
On 13/7/19 12:29 pm, James Arcus wrote:
>
> Hi All,
>
> I'm pleased to say that the Cisco switch chassis/supervisor upgrade on
> Friday was successful. We are now running a Cisco Catalyst 4506-E with
> supervisor 6-E and the latest firmware in place of the previous 4507R
> with supervisor IV. The new switch is named Kerosene and increases
> throughput per line card from 6 Gb/s to 24 Gb/s with the option of 48
> Gb/s with the same chassis in the future. It also adds 10G capability
> and the ability to run the latest software version.
>
> Kerosene is set up nearly identical to Bitumen save for a few things:
>
> * A different management IP that is in DNS
> * The 2xGbE LACP link from Bitumen to Walnut has been replaced with
> 10G SR fibre
> * The connections to Bitumen's 2 24-port line cards have been moved
> onto a 48-port line card
> * Updated rommon firmware and Cisco iOS
>
> The ports have been minimally rearranged to fit the new line cards.
> Essentially, both switches physically consist of 4 rows of 24 ports,
> and the row/column position of each connection has been maintained.
> This is also the tagging system that was used when labelling the ends
> of the patch leads during the move. As the 48-port line card numbers
> ports in top/bottom pairs first (i.e. port 2 is the first port on the
> bottom row, not the second port on the top row), the interfaces in the
> switch configuration had to be renumbered appropriately.
>
> The configs of both Walnut and Kerosene were also altered to use the
> same settings for the 10G link as were previously applied to the
> copper pair. (Failing to remember to change Walnut as well was the
> source of the initial failure for the network to come back up.)
>
> Just a final note on the physical removal/installation of the
> switches: they are very heavy, definitely at least a two-person job.
> For future reference, we found that moving the patch panel underneath
> the switch out of the way allowed lifting it directly up into position
> while mounting, which was much easier.
>
> Thanks to [FVP] and [DAS] for their effort and help.
>
> If anyone has further questions about the process, don't hesitate to
> reply.
>
> Cheers,
>
> James Arcus [MPT]
>
>
> _______________________________________________
> List Archives: http://lists.ucc.asn.au/pipermail/tech
>
> Unsubscribe here: https://lists.ucc.gu.uwa.edu.au/mailman/options/tech/jimbo%40ucc.asn.au
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://lists.ucc.gu.uwa.edu.au/pipermail/tech/attachments/20190713/3bbc356c/attachment.htm
More information about the tech
mailing list